QA testing in *QA-XXXX* has been completed and passed. Ready for deployment in Production.
Summary of test execution details are listed below:
*Test Execution Results*:
% Executed / Plan: 20/20 = 100%
% Passed / Executed: 20/20 = 100%
% Failed / Executed: 0/20 = 0%
% Blocked / Executed: 0/20 = 0%
% Not Testable / Plan: 0/20 = 0%
*Test Plan if:* <link>
*List of Defects* :
1)
2)
*Outstanding / Deferred Defects*:
1)
2)
Quality Sign-Off Criteria
- 100% of the product test plan have been executed
- Minimum 90% pass rate (as a guideline)
- All defects have been logged
- No unresolved critical or high severity defects
- Deferred defects have been reviewed and signed-off by Product Owner/Product Manager for future release
- All test metrics are available for reference